Key Data:
Project type
New motorway section
Construction started
December 2004
Estimated investment
$360m
Key Players:
Sponsor
Transit New Zealand, Northern Gateway Alliance as the operators of the toll, NZ Government, Land Transport New Zealand
Lead contractors
Northern Gateway Alliance, which includes: Transit New Zealand, Fulton Hogan, Leighton Contractors, URS New Zealand (engineering and project management), VSL International (bridge engineering), Tonkin & Taylor (engineering geology and pavement design) and
Others
Halcrow, SIKA NZ, Allied Concrete Ltd, Allianz Global Corporate & Specialty