Key Data:

Order year
2002–2003
Project type
New motorway section
Location
New Zealand
Construction started
December 2004
Estimated investment
$360m
Completion
Mid-2009

Key Players:

Sponsor
Transit New Zealand, Northern Gateway Alliance as the operators of the toll, NZ Government, Land Transport New Zealand
Lead contractors
Northern Gateway Alliance, which includes: Transit New Zealand, Fulton Hogan, Leighton Contractors, URS New Zealand (engineering and project management), VSL International (bridge engineering), Tonkin & Taylor (engineering geology and pavement design) and
Others
Halcrow, SIKA NZ, Allied Concrete Ltd, Allianz Global Corporate & Specialty



Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Events & Exhibitions
Newsletter Archive
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the road traffic industry