Key Data:
Name
Central Motorway Junction
Type
Motorway, viaducts and tunnel
Date of start
2002, 2008-09
Date of completion
2007, 2012-14
Estimated investment
$195m ($55m for stage one, $140m for stage two), two new viaduct projects (costing $482m)
Key Players:
Sponsors / partners
Transit NZ
Contractors (stage one)
Freeflow in an alliance with Transit NZ, Fletcher Construction, Beca Carter Hollings and Ferner Ltd and Higgins Contractors Ltd
Contractors (stage two)
Joint venture between Fletcher Construction Ltd, New Zealand, and Leighton Contractors Pty Ltd, Australia
Designer services
Beca Carter Hollings and Ferner
Services contractor
URS New Zealand Ltd
Sub-consultant
Parsons Brinkerhoff