Key Data:
Cost
$68 million (permanent bridge - $62 million, temporary bridge - $6 million)
Key Players:
Owner
Florida Department of Transportation
Contractors
Traylor Brothers (permanent bridge), Gimrock (temporary bridge)
CEI team
Parsons Brinckerhoff Construction Services, Greenhorne & O'Mara, Williams Earth Sciences Inc., David Fiero & Associates, TRS Consulting Inc., Law Engineering
Superstructure construction engineers
Finley McNary Engineers, Inc.
Feasibility study
Parsons Brinckerhoff
Design
Parsons Brinckerhoff, E.C. Driver & Assoc., FIGG Engineers, Keith & Schnars, Edward D. Stone & Assoc., Helman Hurley Charvat Peacock Architects Inc., David A. Mintz, Inc., META, Schmertmann & Crapps, Arkitex2. Inc