Highway 371 Expansion, Minnesota, United States of America


State Highway 371

Located in central and north-central Minnesota, US, State Highway 371 links the state's northern lakes region with the central region. The highway is being expanded from two to four lanes from Nisswa to Jenkins to improve access along the corridor.

The $58m expansion is being undertaken by the Minnesota Department of Transportation (MnDOT).

Construction on the project commenced in April 2016 and is scheduled to be completed by mid-2017.

Highway 371 expansion project purpose

The Highway 371 improvement project is aimed at providing transportation system improvements to resolve critical travel safety, design deficiencies and capacity problems, as well as reduce congestion.

"Construction on the project commenced in April 2016 and is scheduled to be completed by mid-2017."

The alternatives for Highway 371 improvement included no built, existing alignment, existing alignment with Pequot Lakes bypass, existing alignment with Pequot Lakes and Jenkins bypass, and existing alignment with Jenkins bypass.

The existing alignment with Pequot Lakes was selected as the preferred alternative for the highway expansion. MnDOT completed the draft supplemental final environmental impact statement for the alternative in February 2010. The supplemental final environmental impact statement (SFEIS) was completed in July 2010. Property acquisition for the project was completed between 2010 and 2015.

The plans for the expansion of Highway 371 between Nisswa and Jenkins were announced in October 2014 after obtaining $45m under the Corridors of Commerce funds.

Highway 371 expansion project details

The project will expand a nine-mile (14.48km) section of the Highway 371 between Nisswa and Jenkins to four lanes from the existing two lanes.

The project will add lanes of road and construct a new Cullen Brook bridge in the Nisswa region.

In the Pequot Lakes region, the expansion involves construction of two lanes of road and realignment and addition of easy access points to city roads. A new County Road (CR) 11 interchange with roundabouts will also be constructed, as well as new road links at CR 168/107 and CR 112.

Construction works in the Jenkins region involve a new signalised intersection at CR 16/Meyers Road. The project will also realign the Paul Bunyan Trail and add a new trail bridge over the highway in Pequot Lakes.

Construction on the highway expansion in Minnesota

The pre-construction works, including soil testing and tree clearing along Cullen Brook in north Nisswa were completed between December 2015 and April 2016.

The ground-breaking ceremony for the expansion was held at Brainerd Lakes Chambers of Commerce in Pequot Lakes in April 2016. Earth moving works on site began in July 2016.

Construction of the Paul Bunyan Trail bridge deck was completed in July 2016. The bridge truss sections for the Paul Bunyan trail bridge were delivered in September 2016. Construction works on the Paul Bunyan trail bridge were completed by October 2016.

The concrete materials for the construction of CR 11 bridge in Pequot Lakes were delivered in July 2016. Concrete pouring for the construction of interchanges abutement and piers began in the same month.

Pre-fabricated concrete beams for the construction of the CR 11 bridge were delivered in August 2016. Installation of reinforcement rebar for concrete deck pouring at CR 11 bridge began in September 2016. Paving works for ramps and roundabouts for CR 11 were completed and the road was opened for traffic in October 2016.

Contractors involved

Mathiowetz Construction was awarded the $49.86m design-build contract for the expansion of Highway 371 in November 2015.

WSB & Associates was contracted to provide engineering design services and design quality control oversight for the project in October 2015.