Kallang / Paya Lebar Expressway, SingaporeThe new 12km Kallang / Paya Lebar Expressway (KPE) will run from the East Coast Parkway (ECP) in the south to the Tampines Expressway (TPE) in the North East. The new urban expressway is being constructed at an estimated cost of S$1.8bn. It includes 9km of tunnels, which will make it the longest underground expressway in South East Asia. The KPE will be a dual-carriageway expressway with three lanes in each direction and eight interchanges. "The new urban expressway is being constructed at an estimated cost of S$1.8bn."
In conjunction with the North East Line, the KPE will cater to the growing population in the North East corridor and provide better alternative routes between the city and the estates in the north of the island. It is expected to lighten the load on the Central Expressway (CTE), which is the only expressway now serving the area. Travel time from the North East to the city is expected to be cut by up to 25%. Construction work started in 2001 and is scheduled to be complete in 2008. The agency responsible for the construction is the Land Transport Authority of Singapore. ROUTE OF CONSTRUCTION Starting at the ECP, the Kallang section of the expressway crosses beneath the Geylang River, the National Stadium area, Nicoll Highway, Mountbatten Road, Geylang Road, Sims Avenue and the Pan Island Expressway (PIE). The Paya Lebar section of the expressway continues below the Pelton Canal for almost 2km. It then crosses under Paya Lebar Road and at the same time over the new Circle Line, to reach Airport Road. The tunnels run for nearly 3.5km below Airport Road and Paya Lebar Air Base before emerging at ground level at Defu Lane 3. The expressway then continues at grade for 3km, crossing over Tampines Road on the Kallang Bahru Flyover to meet up with the expressway at Lorong Halus. The new flyover was opened to traffic on 11 September 2005. It provides convenient access for motorists to get on the PIE (Tuas) via Sims Way. The new flyover means that the entire stretch of Sims Way, from the junction of Guillemard Road, Mountbatten Road and Nicoll Highway to the PIE (Tuas), is now also open to traffic. The new road system will include eight interchanges, 11 entry slip roads and 12 exit slip roads. CONSTRUCTION CONTRACTS The main contract for the design, construction and project management of the expressway was awarded to Samsung Engineering and Construction. The construction work for each section of the project was then awarded to subcontractors. "The KPE will cater to the growing population in the North East corridor."
Some of the engineering methods used for the construction of the road are related to the terrain it has to traverse. There are tunnel sections under rivers and also flyover sections, each of these creates its own engineering problems. Construction methods include contiguous bored pile wall, secant pile wall, diaphragm walls and sheet pile walls. ROAD SYSTEMS CONTRACTS Supply, installation, testing and commissioning of the Tunnel Ventilation System (TVS) and Environmental Control System (ECS) is the responsibility of Shinryo Corporation along with Meinhardt. AMEC Group Singapore Pte Ltd is to supply a fire protection gas detection system. Keppel Engineering Pte Ltd is supplying and installing an electrical system that includes high- and low-voltage electrical distribution networks, standby generators, an uninterruptible power supply system and tunnel lighting. Tyco Building Services Pte Ltd are designing, installing and commissioning an Integrated Traffic and Plant Management System (ITPMS). Guthrie Engineering (S) Pte Ltd and Clearsonics are designing and installing the communications systems including the expressway emergency telephone system, radio system, telephone system, public address system and communications backbone network. Chevalier Singapore Holdings Limited is responsible for the design, fabrication and installation of the lift and hoist system for the six ventilation buildings. ROAD CONSTRUCTION CONTRACTS Lam Hong Leong Aluminium Pte Ltd is installing cladding for the expressway. Sembcorp Engineers and Constructors are designing and constructing a 1.5km road tunnel section from ECP to Nicoll Highway, including the construction of the KPE / ECP interchange, the at-grade roads and a ventilation building (Contract 421). "Travel time from the North East to the city is expected to be cut by up to 25%."
SembCorp and Daewoo Joint Venture is designing and constructing a 1.6km road tunnel section from Nicoll Highway to the PIE. This contract includes the construction of the KPE / Nicoll Highway / Mountbatten Road interchange, the KPE / PIE interchange, at-grade roads, pedestrian overhead bridges, covered link-ways and a ventilation building. Samsung Corporation (Engineering and Construction Group) and Mott Macdonald are designing and constructing a 2.96km road tunnel section from PIE to Ubi Road 2 (Contract 423). Taisei Corporation are designing and constructing a 2.6km road tunnel from Ubi Road 2 to Defu Lane 3. The contract includes the construction of the KPE / Bartley Road extension interchange, at-grade roads, pedestrian overhead bridge, bus shelters, covered linkways, sewage lift station, link sewers and two ventilation buildings. Chan & Chan Construction Pte Ltd is constructing a 1km stretch of the KPE from Defu Lane 3 to Fish Farm Road. The contract includes the construction of a dual three-lane flyover across Tampines Road and vehicular bridge over a canal, as well as the widening of part of the Tampines Road. Chye Joo Construction Pte Ltd is constructing a 2km stretch of the KPE connecting Lorong Halus Interchange at TPE to the proposed interchange at Tampines Road. The contract involves the construction of a dual three- to four-lane expressway. CONTRACT 421: ECP TO NICOLL HIGHWAY In the Geylang River section 85% of the tunnel roof has been completed. Once works on the tunnel across the Geylang River are completed, the river will be diverted back onto its original alignment and the river walls reconstructed. Stadium Walk / Stadium Crescent was reinstated on 15 February 2006. Reinstatement works at the Stadium Boulevard / Stadium Drive junction are in progress and was completed in June 2006. The temporary Stadium Drive was realigned to its final location in June 2006 following the backfilling of the KPE and Circle Line (CCL) tunnels below the road junction. "There are tunnel sections under rivers and flyover sections, each creating its own engineering problems."
Another completed section is the KPE tunnel below the ventilation building A. The remaining work is being done by the National Parks Board. Just north of the ECP, the construction of slip road A tunnel structure connecting the northbound KPE tunnel from the city along ECP has been completed. The remaining drain works and surface road works will continue into July 2006. Construction of slip road B tunnel, the exit slip road from KPE southbound tunnel joining ECP (heading towards Changi) is continuing and sheet-piling works are nearly completed. Excavation works and structural works are progressing but rely on the necessary soil-improvement work. Jet grout piles are being installed in the pump sump and shallow end of the slip road due to presence of soft ground below the tunnel structure alignment. Construction of the main tunnel connecting the two tunnel sections at ECP and Tanjong Rhu is also well underway. CONTRACT 423: PIE TO UBI ROAD 2 Contract 423 is one of the most challenging sections of the whole project. This section is almost entirely underground and includes a total cut-and-cover tunnel length of 2.96km, two ventilation buildings, five slip roads, two road bridges and an interchange. The tunnel, which is 36m wide, is located directly below a 27m-wide storm water canal for most of its length and the flow carrying capacity of this has to be maintained at all times during the construction of the tunnels. To add to the complication of the design and construction, the route is adjacent to commercial and residential buildings up to 25 storeys high. Some of these buildings are located only 3m from the completed tunnel structure. The alignment between the Pan-Island Expressway to Aljunied Road, excavation and strut installation works are in full swing. Tunnel construction work is expected to be complete in the middle of 2007, after which the reinstatement of the Pelton Canal and Aljunied Road Bridge will be carried out. The KPE southbound tunnel structures, in front of Blk 122 Paya Lebar Way, were completed in March 2006. Work is now in progress for the construction of the southbound tunnels. The tunnels in the Mattar Road area (from Blk 79/79A to just after the Community Centre) have been completed along with construction of the new Pelton Canal. "The Kallang / Paya Lebar Expressway will provide better alternative routes between the city and the estates in the north of the island."
For the tunnel between Merpati Road and Paya Lebar Road area, the KPE southbound half-box tunnels on the Balam Estate side has been completed since March 2006. Excavation and tunnel construction works for the KPE northbound half-box on the Jalan Chengkek side is currently in progress. Tunnel works in this area are expected to be completed by early 2007, and the Pelton Canal will be reinstated to its original alignment by the end of 2007. Between Paya Lebar Road and Ubi Road 2, tunnel construction works are substantially completed. Reinstatement of Airport Road to its original alignment will be in progress from June 2006 onwards. The basic structure of ventilation building D at the corner of Paya Lebar Road / Airport Road junction has been completed. Architectural as well as Electrical and Mechanical (E&M) works are now in progress. WATERPROOFING SYSTEMS IN CONTRACT 421Waterproofing and substructure waterproofing membrane for tunnel base wall and roof slabs use the Grace waterproofing system, which includes Preprufe pre-applied waterproofing membranes with Bituthene self-adhesive post-applied membranes. About 130,000mē of Preprufe 160R and 300R and 380,000mē of Bituthene 3000 membranes were applied to the tunnel base, wall and roof slabs. Preprufe was selected for its unique positive bonding system, where it bonds to wet concrete poured against it. It can be laid on damp surface substrates as it does not bond to lean concrete. As soon as it is laid, reinforcement bars can be placed on it almost immediately, requiring no protection screed. This helps to speed up installation and the construction cycle. Furthermore, Preprufe can be installed effectively in confined areas, for example, around sheet piles, and yet provide a positive waterproofing system.
|
![]() The route of the new 12km Kallang / Paya Lebar expressway. | |
![]() Construction work on one of the expressway's cut-and-cover tunnels. | ||
![]() The new Kallang Bahru flyover during construction. | ||
![]() The effect of the new flyover on the operation of the surrounding road infrastructure. | ||
![]() Expressway construction work at Tanjong Rhu road. | ||
![]() Backfill work underway at Tanjong Rhu road. | ||
![]() Strutting work along the Jaylong River. | ||
![]() One of the six ventilation buildings supplying fresh air to the tunnels. |
