|
The Uetliberg Tunnel is part of the new N4/N20 Zurich western bypass in Switzerland and is the largest tunnel and stretch of roadway of the bypass at 4.4km. The tunnel represents one element in a large road transport project; it links the Birmensdorf bypass (N20.1.4) in the west with the existing Zurich-Chur motorway (the A3) in the east. Completion of the Uetliberg tunnel fills a considerable hole in Switzerland's road network as well as providing a quick, environmentally friendly and convenient traffic diversion away from the centre of Zurich. Under the management of the Engineering Department of Canton Zurich, the Office of Civil and Underground Engineering, the National Highways department and Zurich/CH, the Uetliberg Tunnel project began in 2000; design and planning was started in 1982 in conjunction with Amberg Enegineering. The tunnel will open in late 2008. The total cost of the project has been estimated at CHF1.12bn. Project design and coordination as well as tunnelling and construction supervision was undertaken by Amberg Engineering Ltd., Regensdorf. Other contractors to contribute on the Uetliberg Tunnel project include Fietz AG, Henauer + Gugler AG, Alpine Mayreder Bau GmbH, CSC Impresa Costruzioni SA, Murer AG, Prader AG Tunnelbau, Wayss & Freytag Ingenieurbau AG, Zschokke Locher AG, Stahlton AG, SikaBau AG of Zurich (waterproofing system), SpannStahl AG (prestressing), Hans Eichenberger AG and Joint Venture "Uetli" (Zschokke Locher, Zurich, Murer AG, Prader AG, CSC Bauunternehmung AG, Wayss & Freytag, Alpine Mayreder Bau GmbH, ZüblinSchlittlerSpaltenstein Bau AG). "The total cost of the project has been estimated at CHF1.12bn."
With two parallel tubes of the same length, each tunnel tube comprises two lanes and a hard shoulder (gradient 1.6%) with a total carriageway width of 10.5m. On the straight, the camber is 2.5% and 5% on the bends. The tunnelling has been carried out from two portals: Wannenboden in the west and Gänziloo in the east. After a five-week installation period, a Tunnel Boring Machine (TBM) with a diameter of 5m started operations in the northern tunnel of the western portal, driving a pilot tunnel through a 2,800m section of the Uetliberg molasse. The TBM reached the oncoming excavation after seven months and was subsequently pulled back through the pilot tunnel to begin tunnelling on the southern tunnel. The same TBM was later used to extend both tunnels to their final cross-sections of 14.4m using a Tunnel Bore Extender (TBE) with an under-cutting section, used for the first time in the world. STANDARD TUNNEL CROSS-SECTIONThere are two differing cross-sections of the tunnel, owing to the composition of ground in the Uetliberg and Eichholz sections of the tunnel. In the Uetliberg cross-section, the excavation area totals 159m² with a width of 14.4m and a height 14.2m. The tunnel seal in the Uetliberg cross-section is drained and unpressurised due to the dry molasse. In the Eichholz and soft-ground sections there is a tunnel cross-section of 14.5m width and 12.50m height. Total excavation area totals 143.3m². In these areas, the seal is pressure-maintaining. There are three main areas inside the tunnel cross-section: a road area, substructure featuring a service duct and exhaust air duct, housed in a false ceiling. Within the service duct, a hydrant pipe is housed, along with the main drainage pipe from the carriageway as well as electromagnetical equipment. The tunnel cross-section comprises of two lanes and a hard shoulder resulting in a total carriageway width of 10.5m. Tunnel camber is 2% on the straight and 5% on the bends. A 1m-wide verge is situated on each side of the carriageway as well as slotted channels for the drainage of the carriageway and the discharge of liquids following any accidents that occur. The tunnel features cross-cuts every 300m connecting the two carriageway tubes. Every third cross-cut is accessible to vehicles. In addition, both tunnels have hydrant and SOS refuges at 150m intervals as emergency measures. TUNNEL VENTILATIONThe Uetliberg Tunnel's main ventilation is situated in the Reppisch valley towards the western tunnel portal. The station is connected to an exhaust vent gallery via a vertical shaft which has an exhaust flue on the Ettenberg Mountain. The station was built by carrying out a cut and cover excavation, which was about 230m long. The vent gallery has a cross-section of approx. 50m² and the vertical shaft a cross-section of 17m². Using a system of longitudinal ventilation, the air flow was generated by a natural piston action created by moving traffic. Exhaust air can flow freely out of the portals at the eastern end of the tunnel. Due to environmental constraints, emissions must be eradicated at the western portal. This means that the exhaust from this side is collected by the Reppisch valley ventilation station and then removed via the exhaust air shaft. In the event of traffic queues or fires, exhaust air is extracted via the false ceilings of either tunnel tubes and carried via the Reppisch valley ventilation station to the ventilation flue. TUNNEL BORING MACHINEThe TBM used in the Uetliberg molasses section of the tunnel had a diameter of 5m. In addition, a Tunnel Bore Extender (TBE) is braced in the pilot tunnel and used to widen the pilot tunnel to the full cross-section diameter of 14.4m. Safety equipment, such as cable bolts, Swellex rock bolts, shotcrete and mesh have all been used to secure the tunnel behind the boring head. MATERIALS HANDLINGBecause of the size of the Uetliberg Tunnel, a large amount of spoil material is produced. This totalled around 1,700,000m³ of solid spoil and mud material. Over 70% of this was generated from the Reppisch valley cut-and-cover works. "The tunnel cross-section comprises of two lanes and a hard shoulder resulting in a total carriageway width of 10.5m."
Because these materials could not be reused at any point in the project, they need to be removed from the site. All spoil material produced by tunnelling in the soft ground was trucked to the Landlikon portal where conveyor belts carried it via a crusher plant. Where the TBM is operating in the molasse sections of the tunnel, all spoil was taken straight from the working face via a continuous belt system 1,760m in length taking material to a rail loading area in the Filderen area. All spoil was taken to local gravel pits. WATERPROOFINGIn the Uetliberg Tunnel zone, in the loose soil zones the tunnel waterproofing was executed in different ways. In the majority 2 and 3mm-thick polymer waterproofing membranes on synthetic fleece and/or drainage mats were used (360,000m²) to prevent water infiltration from the pressure-containing section into the non pressure-containing section. The water pressure-containing waterproofing system consists of a single, monitorable and injectable membrane layer with 'Rückfallebene' (second defence line). The waterproofing membrane was fastened by a VELCRO system. |
![]() Expand ImageThe Uetliberg Tunnel, part of the new N4/N20 Zurich western bypass in Switzerland, is the largest tunnel and stretch of roadway of the bypass at 4.4km. |
![]() Expand ImageBasel tube. | |
![]() Expand ImageAerial view of the assembly area Landikon including construction areas Reppischtal and Schacht Eichholz. | |
![]() Expand ImageProfile of Uetliberg Tunnel. | |
![]() Expand ImageBoring at section Diebis. | |
![]() Expand ImageAssembly of tunnel boring machine (diameter 5m). | |
![]() Expand ImageLocation map of Swiss highways around the Uetliberg Tunnel. (All images copyright: Amberg Engineering Ltd.) |