Stonecutters Bridge Hong Kong, China

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Bridge type
Cable-stayed highway bridge (semi-fan arrangement)
Length
1,596m
Main span
1,018m
Pylon height
295m
Length of side spans
2 x 289m
Deck width
51m (including 14m gap between the two carriageways)
Pylon foot
24m x 18m

Work will commence on Angchuanzhou Bridge, otherwise known as Stonecutters Bridge, in 2004. By the time it is completed in 2009 the bridge will be the longest of its type in the world, with a span of 1,018m and an overall length of 1,596m. Straddling the Rambler Channel at the entrance to the busy Kwai Chung Container Port, it will form part of Route 8 which links Tsing Yi and Cheung Sha Wan.

The bridge will span the Rambler Channel from the back-up land of Container Terminal 8 (CT8) at the eastern side on Stonecutters Island to the back-up land being formed for Container Terminal 9 (CT9) on Tsing Yi Island.

STONECUTTERS BRIDGE DESIGN
"The bridge will be the longest of its type in the world, with a span of 1,018m and an overall length of 1,596m."

The design concept for the bridge was procured by Highways Department in Hong Kong through an international design competition and the winning scheme by a group consisting of Halcrow Group, Flint & Neill Partnership, Dissing + Weitling and Shanghai Municipal Engineering Design Institute was selected as the Reference Scheme for the further design development. A group led by Ove Arup & Partners with COWI Consulting Engineers A/S and BMT Asia Pacific Ltd as sub-consultants has carried out the further design development of the Reference Scheme (RS) and the detailed design that followed.

In 2004 the US$350m contract to construct the bridge was awarded to the international consortium Maeda-Hitachi-Yokogawa-Hsin Chong Joint Venture (MHYHC). Nippon Steel of Japan is supplying the cable stays for the bridge which are first tested by CTL Group. The longest stay cables supporting the bridge superstructure are more than 670m (2,198ft) long.

The testing programme began in October 2005 and continued through the middle of 2006. The test programme was conducted in accordance with the SETRA/CIP recommendations on cable stay design and construction, and includes fatigue tests, tensile strength tests and a first-of-its-kind cable corrosion protection system aging and watertightness test. The cables consist of parallel 7mm galvanised wire with HiAM anchorages, and they range in size from 187 to 421 wires. Maunsell AECOM was appointed by MHYHC as a consultant on the construction.

STONECUTTERS BRIDGE DESIGN

The concept is for a cable-stayed bridge with a twin 53m-wide aerodynamic deck (split into two steamlined boxes connected by cross girders) suspended from two 300m-high concrete and stainless steel single pole towers. These towers will have bases measuring 24m x 18m tapering to 7m diameter at the top, and the deck will allow a navigation clearance of 73.5m over the full entrance to the Container Port.

The two towers will be in concrete until level +175m and in composite construction consisting of an inner concrete ring with a stainless steel skin for the top 120m. The original concept had a conventional steel structure above level +175m but Arup found that this configuration would be too lively and lead to unacceptable vibrations of the stay cables.

Using a heavier composite section instead of a pure steel structure solved this problem. For reasons of durability and to enhance the appearance, further studies concluded that the tower skin should be fabricated from a duplex stainless steel (grade 1.4462 to BSEN10088) with a shot peened surface finish. The deck itself will be made of steel in the main span and of concrete in the side spans.

The tower foundations will be located within 10m of the seawall on either side of the Rambler Channel, close to the back-up land next to CT8 and CT9. Their proximity to the channel necessitated ship impact testing and modeling. Geotechnical centrifuge testing was conducted using a 1:200 scale model of a vessel bow section and seawall within a container.

STAINLESS STEEL STUDIES FOR TOWERS

Arup chose to investigate the practically and suitability of using stainless steel for such a large-scale application. The study led Arup to design and supervise the construction of a prototype fabrication that was representative of a typical section of the tower. The prototype was made in two halves, each approximately 1.75m high and 7m curved on plan – the two halves were connected by a bolted flange as is the actual structure.

"The bridge is a major component of the $17bn Route 9 that runs from Tsing Yi to Cheung Sha Wan."

The fabrication also included roll forming plates to a conical shape, fabrication of typical details (including stiffeners and studs to the reverse face) and establishing the finish that can be achieved by shot peening on a large fabrication.

The fabrication was undertaken by Ancon Building Products, Sheffield, the hot rolled steel plate were supplied by AvestaPolarit, with the roll forming being carried out by Barnshaw Bending and the surface finishing by Metal Improvement Company, Derby.

The prototype was completed successfully and was able to show the feasibility of fabricating the towers from stainless steel and of achieving an acceptable level of finish on hot rolled plate. Graham Gedge, a materials project manager for Arup who was the consultant on the project, said: "The key driver for considering alternative materials for the upper tower skins was the need to provide a long-term maintenance-free life of 120 years, and this would not have been possible with structural steel."

WIND STUDIES

The Hong Kong region is susceptible to very strong typhoon winds, a fact that is being taken into account in the design of the bridge. In October 2002 a 50m mast was erected at the site to measure the speed, direction and turbulence of winds in the area. Readings, which will continue until at least January 2004, are transmitted in real-time to an offsite location for further analysis.

In particular, the stability of the 509m-long cantilevers during construction required special consideration in the design. Although the Hong Kong design standards contain severe requirements for wind loading then it is essential for a project of this scale and nature that the wind climate of the actual site is taken into account in the design.

ROUTE 9 (TSING YI – CHEUNG SHA WAN)

The bridge is a major component of the $17bn Route 9 that runs from Tsing Yi to Cheung Sha Wan and connects the island of Tsing Yi and Kowloon. Also, along with the other two major elements of the route (Ngong Shuen Chau Viaduct in the east and Nam Wan Tunnel in the west respectively) it will form a strategic link, providing a relief route to the existing Route 3 between Tsing Yi and Kwai Chung Section.



Expand Image Expand Image
The Stonecutters Bridge, when completed, will be a major new landmark for Hong Kong.



Expand Image Expand Image
The chosen design was for a cable-stayed bridge with a twin aerodynamic deck suspended from two 290m-high single pole towers.



Expand Image Expand Image
The bridge will span the Rambler Channel from Container Terminal 8 on Stonecutters Island to Container Terminal 9 (CT9) on Tsing Yi Island.



Expand Image Expand Image
The Stonecutters Bridge will be part of the dual three-lane Route 9.



Expand Image Expand Image
The bridge forms a vital part of Route 8 in Hong Kong.



Expand Image Expand Image
The top of the tower is clad with stainless steel 20–30mm thick.



Expand Image Expand Image
Construction of the deck is proceeding and the bridge should be completed by 2009.



Expand Image Expand Image
One of the towers under construction.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the road traffic industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Events & Exhibitions
Newsletter Archive
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the road traffic industry