Key Data:
Structural type
Cable-stayed bridge multicable, fan arrangement
Function
Highway bridge to carry the A75
Location
Near Millau, Aveyron, France
Timescale
Works started in October 2001 and was completed in December 2004
Number of workers on site
350-480
Number of hours of work expected
1 million
Owners
Compagnie du viaduct de Millau
Architect
Lord Norman Robert Foster
Geotechnical engineering
Terrasol
Co-contractor
Eiffel Construction Metallique
Design:
7 Pylons
Reinforced concrete
Dimensions:
Height above valley bottom or water
Max 270m
Material Required: