| A86 West Tunnel, | ||
The A86 West will form the final link of the A86 ringroad around Greater Paris. |
The total project cost of the A86 West is €2.23 billion. |
The tunnels are being constructed using an all terrain, made to measure tunnel boring machine. |
Utilising a laser guiding system the TBM follows a precise boring course which cuts an average of 30m every day. |
The installation of arch segments constructed from prefabricated reinforced concrete provide the structural finish to each tunnel. |
An information system will automatically collect traffic data. This information is relayed to a safety and control office to allow quick and effective control of vehicles entering and exiting the tunnel. |
The A86 West will be formed of two tunnels; one double deck for light vehicles, the other single deck for all vehicles. |
The A86 West Tunnel has a number of ventilation units to ensure a permanently renewed atmosphere with efficient smoke extraction. |
An emergency access shaft; there are five situated in the West tunnel and four in the East tunnel. |
The East tunnel is exclusively for light vehicles with 2m-clearance height and will feature two decks each with three lanes. |
The entrance to the West tunnel from the A13 motorway; the A13 interchange will now not be open until Spring 2008. |
|
| Addison Airport Toll Tunnel, Dallas, TX | ||
In September 1997, tunnelling crews started constructing a two-lane vehicular toll tunnel under Addison Airport. |
Addison Airport tunnel was excavated to a horseshoe configuration 40ft-wide by 28ft-high. |
Zachry's team completed the project using specialised tunnelling equipment in varying terrain, soils and climates. |
Addison Airport tunnel has six-lane toll plaza. |
||
| Airside Road Tunnel (ART) Heathrow Airport, London | ||
During boring the new tunnel passed within 3m of the operating Heathrow Express rail tunnels. |
Each end of the tunnel has 500m of ramp leading into the portals. |
Steelwork was designed to support the new ART during construction. |
The tunnel boring machine (TBM) was supplied by HerrenKnecht. |
The 1.3km-long tunnel is constructed as twin bore and cost £140m. |
The tunnel took just over a year to construct and opened in March 2007. |
| Devil's Slide Tunnels | ||
The Devil's Slide Tunnels project is taking place on part of the route of the Pacific Coast Highway. |
The highway in the area has experienced frequent expensive damage from landslide activity in the past, leading to the Devils Slide Tunnels being chosen as a solution to the problem. |
The Devil's Slide Tunnels scheme will bypass the ecological issues previously associated with the highway. |
The twin bridges at the north end of the Devil's Slide project will be complete by summer 2008. |
Contractor Kiewit Pacific will use two 120t Austrian-made 'roadheader' machines for the majority of the tunnelling on the project. |
|
| Dublin Sea Port Tunnel | ||
The Dublin Port Tunnel will provide a eight-minute link between the port and the M50 for some 20,000 vehicles per day. |
The Dublin Port Tunnel is a 6.5km long dual carriageway, 4.5km of which is fully underground. |
The vertical shaft at Whitehall is the largest European shaft built to date and has resulted in the excavation of over 84,000m³ of earth. |
The shaft was constructed using the diaphragm walling method. |
The 11.8m-diameter Herrenknecht TBM (nicknamed Gráinne) was delivered to the shaft in 103 parts. |
Detail of the Herrenknecht TBM. |
The Dublin Port Tunnel is open to all types of traffic, although some trucks may not fit under its 4.65m height. |
Construction of the tunnel began in 2001 and boring ran from in two directions from Whitehall and back. |
Transroute International is the operator of the Dublin Port Tunnel for a five-year period. |
| Eiksund Undersea Tunnel | ||
Map showing route of tunnel. |
Ørsta bolt – 37,000 bolts were used in the tunnel’s construction. |
Tunnelling operations underway. Note the conduit services line in the ceiling. |
Engineer on a gantry carrying out a survey of the tunnel ceiling. |
Truck and digger removing spoil from tunnel entrance. |
Slurry cement process underway. |
CT bolts being placed to support tunnel walls and ceiling. |
||
| Göta Tunnel, Gothenburg | ||
Map showing the area of Götaleden with the route of the new road tunnel. |
Cross section schematic showing the two tunnels. |
The Göta Tunnel on its day of opening. |
Graphical representation of the redeveloped Södra Älvstranden area. |
Gothenburg Opera House, which will be linked to the city centre once the Södra Älvstranden area has been developed. |
The area of Södra Älvstranden in February 2007, with nearby businesses already undergoing face lifts in preparation for the new open Södra Älvstranden. |
Södra Älvstranden in February 2007. |
||
| Grouft Tunnel | ||
The Grouft Tunnel will be sealed with a membrane and finished with shotcrete. |
The flexible sealing membrane. |
Work on the rescue tunnel. |
The downhill tunnel will have two lanes and the uphill tunnel three lanes. |
The north portal of the Grouft Tunnel. |
|
| Herren Tunnel, Lübeck | ||
The Herren Tunnel is a road tunnel in Lübeck opened in August 2005. |
The Herren Tunnel replaces the ageing bridge over the Trave River. |
The tunnel was sealed by lining it with 3,640 prefabricated concrete segments, put in place immediately behind the TBM. |
The Herren Tunnel is a twin parallel tube tunnel. |
The twin tunnels were mainly cut using a TBM. |
The cutting edge of the TBM. |
The TBM being assembled in the access shaft. |
Excavation for one of the ramps to lead to the tunnel entrance. |
Components of the TBM being transported for assembly. |
The interior of the tunnel before the road surface was laid. |
The entrance of the finished Herren Tunnel. |
Herren Tunnel toll booths. |
| Lane Cove Tunnel, Sydney | ||
The Lane Cove Tunnel is a key link in Sydney's orbital motorway network. |
Artist's impression of the entrance / exit road from the Lane Cove Tunnel. |
Looking east at the junction of Epping Road and Mowbray Road West in Lane Cove, with the western portals of the tunnels on the right. |
Alpine Miner ATM 105-IC roadheaders from Voest. |
Looking west along Longueville Road at the new Parklands Avenue bus interchange, connected to the Lane Cove shopping centre by a new pedestrian bridge. |
Looking west along the rebuilt Gore Hill Freeway under the rebuilt Reserve Road bridge. |
One of the pedestrian and cycle ramps installed as part of the project. |
The eastern end of the tunnel, which begins as two lanes and then turns into three. |
The Gore Hill Freeway has an additional new lane in each direction to act as transit lanes. |
| Medway-Canvey Island Thames Crossing | ||
The new Medway-Canvey Island crossing is still at the design stage, but a proposal has been made to the DfT and the EA. |
Canvey Island will be central to the whole scheme which could include a tidal power station and a further tidal barrier. |
The Thames Estuary has always been a natural barrier between Kent and Essex. |
The Department for Transport and the Environment Agency are investigating proposals for a project to link Medway and Canvey Island. |
The rail tunnel part of the proposed Medway-Canvey Island project will carry a line to link with the Crossrail project in London. |
The Medway-Canvey Island tunnel will be laid in a trench dredged across the bed of the Thames Estuary. |
| Nam Wan Tunnel | ||
Blast doors to muffle the sounds of blasting during the Nam Wan Tunnel construction. |
Inside the westbound tunnel. |
Tunnel ventilation jet fan. |
Smoke extraction vents being installed. |
Installation of vitreous enamel panel supporting frame. |
A computer-generated image of the Nam Wan Tunnel portal. |
Construction of the Nam Wan Tunnel and motorway. |
Nam Wan Tunnel portal retaining wall. |
|
| New Tyne Crossing | ||
The new Tyne tunnel will be constructed alongside the old tunnel to ease congestion. |
The New Tyne Crossing project will cost £260m and will refurbish the old tunnel as well as constructing a new one. |
Currently, on the existing Tyne Tunnel, there are severe traffic issues as the road narrows from a dual carriageway to a single carriageway. |
Traffic congestion through the tunnel has a negative effect on the A19, particularly during busy periods. |
The new Tyne Tunnel will be completed and the old tunnel refurbished by 2011. |
|
| Route 29 Tunnel, Trenton, NJ | ||
Looking north, completion of the remedial excavation and backfill at the foot of Lalor Street (December 2000). |
Looking northwest, placement of the AASHTO precast girders for the Ramp D bridge which will connect with Lalor Street. |
Looking east to homes on adjacent Lamberton Road, a front end loader clears dirt from a section of the project (March 2000). |
Workers prepare the river bank for the new road in June 1999. |
||
| Saaser Tunnel | ||
Robit forepoling of steel piles drilled into the soft ground. |
Bolting with Tamrock jumbo. |
Part of the escape system of the tunnel. |
Tunnel boring machine. |
Map showing the location of Saas. |
|
| San Cristóbal Tunnel | ||
The San Cristóbal tunnels were excavated using drill and blast methods. |
The San Cristóbal tunnels are only in limited use at the current time. |
The tunnel has escape exits and refuges at regular intervals along its length. |
The northern portal of the San Cristóbal tunnels. |
The San Cristóbal tunnel is part of a larger 4km-long project linking the business areas of Santiago to the northern suburbs. |
|
| SMART (Stormwater Management And Road Tunnel), Kuala Lumpur | ||
Installation of toll booths. |
Map showing the location and route of the stormwater tunnel. |
Graphical representation of a cross-section of the tunnel. |
Storm Control Centre. |
Road showing tunnel toll booths. |
One of the 2 x 13.2m diameter tunnel boring machine – one of the world’s largest. |
One of the tunnel boring machines. |
Schematic showing how the tunnel will work in differing climatic conditions. |
|
| Thu Thiem Tunnel | ||
The new District 2 is set to become a prosperous commercial centre. |
Construction was delayed because of difficulties encountered during site clearance. |
Lack of road development in Ho Chi Minh City has lead to heavy traffic. |
The tunnel project is part of the larger East-West highway project. |
The centre of Ho Chi Minh City during rush hour. |
|
| Tunnel du Mont Sion | ||
The TBM has already completed the first drive. |
The precast yard will produce all the tunnel linings. |
There is also the service infrastructure for disposing of tunnel spoil and maintenance. |
The TBM was christened Adelaide in October 2006. |
The cutting surface. |
The second tunnel drive to the east is due to started in mid-2007. |
| Uetliberg Tunnel, Zurich | ||
The Uetliberg Tunnel, part of the new N4/N20 Zurich western bypass in Switzerland, is the largest tunnel and stretch of roadway of the bypass at 4.4km. |
Basel tube. |
Aerial view of the assembly area Landikon including construction areas Reppischtal and Schacht Eichholz. |
Profile of Uetliberg Tunnel. |
Boring at section Diebis. |
Assembly of tunnel boring machine (diameter 5m). |
Location map of Swiss highways around the Uetliberg Tunnel. (All images copyright: Amberg Engineering Ltd.) |
||
| Westerschelde Tunnel | ||
The two twin-tunnels of the Westerschelde Tunnel run 12m apart and have two 3.5m wide lanes for traffic each. All images courtesy of NV Westerschelde Tunnel. |
With an estimated cost of €726 million, the Westerschelde Tunnel will provide a faster and more economical route for around 27,000 vehicles a day between Ellewoutsdijk in Zuid-Beveland and the Zeeuws Vlaanderen region near Terneuzen. |
The Westerschelde tunnel boring machines (TBM) worked for 24 hours a day, six days a week to meet construction targets. |
Inside the 8m cylinder hydro shield under the Westerschelde. |
One of the 53,000 concrete lining segments being put in place. |
The particular challenge that faces the construction of this tunnel is the soft clay that has to be bored through. |
The fire protection sheathing of the tunnel is designed for a fire-load of 1,350ºC. |
The two tunnels are the deepest ever to be driven worldwide and are the greatest challenge to date in terms of machine layout, processing and construction. |
|
| Yangtze River Tunnels | ||
The Yangtze River tunnels are being constructed using two TBMs. |
The under-river tunnels will link the mainland with the island of Changxing. |
The two tunnels will require the disposal of 2.7 million cubic metres of earth by the time they are completed. |
The twin tunnels across the Yangtze river will be completed by 2010. |
Tunnelling with the first TBM began in September 2006, with work on the second tunnel beginning in December that year. |
The two TBMs being used for the Yangtze River project are the largest in the world with a diameter of 15.43m. |